TABLE 1-A – BUILDING PERMIT FEES
|
TOTAL VALUATION |
FEE |
|
$1.00 to $500.00 |
$23.50 |
|
$501.00 to $2,000.00 |
$23.50 for the first $500.00 plus $3.05 for each additional $100.00, or fraction thereof, to and including $2,000.00 |
|
$2,001.00 to $25,000.00 |
$69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00, or fraction thereof, to and including $25,000.00. |
|
$25,001.00 to $50,000.00 |
$391.25 for the first $25,000.00 plus $10.10 for each additional $1,000.00, or fraction thereof, to and including $50,000.00 |
|
$50,001.00 to $100,000.00 |
$643.75 for the first $50,000.00 plus $7.00 for each additional $1,000.00, or fraction thereof, to and including $100,000.00 |
|
$100,001.00 to $500,000.00 |
$993.75 for the first $100,000.00 plus $5.60 for each additional $1,000.00, or fraction thereof, to and including $500,000.00 |
|
$500,001.00 to $1,000,000.00 |
$3,233.75 for the first $500,000.00 plus $4.75 for each additional $1,000.00, or fraction thereof, to and including $1,000,000.00 |
|
$1,000,001.00 and up |
$5,608.75 for the first $1,000,000.00 plus $3.65 for each additional $1,000.00, or fraction thereof |
|
Other Inspections and Fees: |
||
|
1. |
Inspections outside of normal business hours (minimum charge – two hours) |
$47.00 per hour1 |
|
2. |
Inspections for which no fee is specifically indicated (minimum charge – one-half hour) |
$47.00 per hour1 |
|
3. |
Additional plan review required by changes, additions, or revisions to plans (minimum charge – one half hour) |
$47.00 per hour1 |
|
4. |
For use of outside consultants for plan checking and inspections, or both |
Actual costs2 |
1Or the total hourly cost to the jurisdiction, whichever is the greatest. This cost shall include supervision, overhead, equipment, hourly wages and fringe benefits of the employees involved.
2Actual costs include administrative and overhead costs.